SALAM

Friday, June 17, 2011

TIMELINE : PROPOSED SOLUTION TO MAHALLAH AT-TABARI AND IM-2 PROBLEMS

From: SHAFFEI BIN MOHAMAD [mailto:shaffei@iium.edu.my]

Sent: Friday, June 17, 2011 4:59 PM

To: Tan Sri Mohd Sidek b. Hassan; Rahmah binti. Ramli

Subject: RE: PROPOSED SOLUTION TO MAHALLAH AT-TABARI AND IM-2 PROBLEMS

Assalammualaikum wbt.

Dear YBhg. Tan Sri,

I apologise about that. As requested, here are the details of timeline for the renovation works:

PROPOSED SOLUTION TO MAHALL AT-TABARI AND IM-2 PROBLEMS

I. Mahallah At-Tabari

Ventilation problem and solution

1. To change fix panel window glass to air lourves and add ventilation fan for each room.

- 2 months to complete (From 21st June 2011 until 20th August 2011)

2. To provide partition for all rooms for privacy but will reduce the no of occupant of 2 for each room.

- 2 months to complete (From 21st June 2011 until 20th August 2011)

3. To provide table light for all.

- 2 weeks to complete. (From 6th August 2011 until 20th August 2011)

4. Cloth hanger room for all blocks.

- 1 month (From 22nd July 2011 until 20th August 2011)

5. To setup a fellow, principal and TV room.

- 1 month to complete. (From 22nd July 2011 until 20th August 2011)

Overall renovation works date is from 21st June until 20th August 2011

_________________________________________________________________________

II. Mahallah IM-2

Ventilation problem at ground level and solution

1. To scrap off the suspended ceiling (increase height) for allowing the ventilation flow.

- 1 month (From 21st June 2011 until 21st July 2011)

2. Rewiring for additional ceiling fan and extractor fan.

- 2 months to complete (From 21st June 2011 until 20th August 2011)

Overall renovation works date is from 21st June until 20th August 2011

________________________________________________________________________

III. Facilities for the disabled students at Gombak campus

1. Upgrading of disabled toilet at Mahallah Uthman

- Status: completed

2. To construct concrete ramp near the bridge connecting Kulliyah of Economic and Kulliyah of Law

- 14 days to complete

Construction date is from 13th June until 27th June 2011

_________________________________________________________________________

As for your 2nd query, Yes, the student is most interested in the loops. I have also included Br. Amir in this email.

_________________________________________________________________________

Thank you, wassalam.

No comments: